Four (4) month long project of providing all labor, equipment, supervision and project management support in the total construction of a new electrical substation in direct support of a large wind power project in Washington.
Completed all civil work inclusive of trenching, concrete pillars/foundations, drainage, etc. In addition provided all welding materials to complete exothermic welding necessary to install a complete ground grid system. Installed conduit, cable, conductors, terminations, steel structures, breakers, insulators, shunt capacitor bank, and buss. Procured all stainless steel hardware needed to complete the terminations of the overhead conductors and/or buss connections. Rigged and placed control building on its foundation and completed all electrical terminations. Installed area security fencing around the entire switchyard. Assisted with required testing and commissioning.